Nsi Vitrum An advanced life science research facility under development at st. john’s innovation park in cambridge, this project aims to create 175,000 square feet of adaptable laboratory and office space, designed with sustainability and occupant wellbeing in mind. Photo shown is only an indicative representation of colour and design. it is strongly recommeded before deciding on your colour design, to view a full slab, or a physical sample. photo shown is only an indicative representation of colour and design.
Vitrum Exigere Working with mclaughlin & harvey ltd alongside breakthrough properties, henning larsen feilden mawson, exigere and third london wall, vitrum aims to create 175,000 square feet of adaptable. With construction set to be completed during 2026, it will offer high performance spaces for scientific discovery within the north east cambridge innovation cluster. click here to find out more about our involvement on this project below. Earlier this year we carried out an inspection of the visual mock up (vmu) for the vitrum project—a key moment in refining the façade solution and ensuring it meets the high standards set for. Our vmu for the vitrum project in cambridge has been approved. this advanced life science research facility will provide 175,000 square feet of adaptable laboratory and office space, designed with sustainability and occupant wellbeing at its core.
Vitrum Colorminium Earlier this year we carried out an inspection of the visual mock up (vmu) for the vitrum project—a key moment in refining the façade solution and ensuring it meets the high standards set for. Our vmu for the vitrum project in cambridge has been approved. this advanced life science research facility will provide 175,000 square feet of adaptable laboratory and office space, designed with sustainability and occupant wellbeing at its core. We’ve now completed all window frames and glazing across levels 00 to 04, with external sealing works also fully finished. external fire stopping and insulation are nearly complete, and cladding installation has commenced on the east elevation. Colorminium are proud to be actively seeking to address the skills shortage in the construction industry by creating strategic partnerships with technical schools universities. • vitrum – external works nearing the final stages, with hoist infill, ground floor curtain wall and terrace elements progressing well. • 20 giltspur street – first curtain wall area handed over and internal handovers now underway. Colorminium has shaped the london skyline for almost 50 years with our unique approach and expertise. we are creative thought leaders and industry challengers on a mission to build a better future for london.
Vitrum Colorminium We’ve now completed all window frames and glazing across levels 00 to 04, with external sealing works also fully finished. external fire stopping and insulation are nearly complete, and cladding installation has commenced on the east elevation. Colorminium are proud to be actively seeking to address the skills shortage in the construction industry by creating strategic partnerships with technical schools universities. • vitrum – external works nearing the final stages, with hoist infill, ground floor curtain wall and terrace elements progressing well. • 20 giltspur street – first curtain wall area handed over and internal handovers now underway. Colorminium has shaped the london skyline for almost 50 years with our unique approach and expertise. we are creative thought leaders and industry challengers on a mission to build a better future for london.
Vitrum Colorminium • vitrum – external works nearing the final stages, with hoist infill, ground floor curtain wall and terrace elements progressing well. • 20 giltspur street – first curtain wall area handed over and internal handovers now underway. Colorminium has shaped the london skyline for almost 50 years with our unique approach and expertise. we are creative thought leaders and industry challengers on a mission to build a better future for london.